Major Utility Projects Happening |
|||
|
|
Puget Sound Energy (PSE) |
|
Project: | Ballinger Gas Line Replacement | ||
Location: | Ballinger Neighborhood | ||
About: |
|
Puget Sound Energy will replace existing steel and steel wrapped natural gas main with approximately 1490 lineal feet of 4" main. The new gas transmission main starts in the intersection of 15th Ave NE and Ballinger Way NE. The main then heads east on NE 205th St to 20th Pl NE. West of Gateway Place and at 19th Ave NE, approximately 120 lineal feet of main crosses county line into the City of Mountlake Terrace. | |
Schedule: | Gas work to be completed in late Fall, restoration to follow. | ||
Impacts: | Expect traffic delays. Typical hours of operation are 9:00am to 3:00pm. | ||
![]() |