Puget Sound Energy (PSE)
Contact: Justin McConachie, 425-457-5777 
www.pse.com

Project: Ballinger Gas Line Replacement
Location: Ballinger Neighborhood
About:

Puget Sound Energy will replace existing steel and steel wrapped natural gas main with approximately 1490 lineal feet of 4" main. The new gas transmission main starts in the intersection of 15th Ave NE and Ballinger Way NE. The main then heads east on NE 205th St to 20th Pl NE. West of Gateway Place and at 19th Ave NE, approximately 120 lineal feet of main crosses county line into the City of Mountlake Terrace.
Schedule:   Gas work to be completed in late Fall, restoration to follow.
Impacts: Expect traffic delays. Typical hours of operation are 9:00am to 3:00pm.