Major Utility Projects Happening
in the City of Shoreline – Fall 2011
 
For Capital Improvement Projects (CIP), please visit our CIP Map page

   

Qwest / CenturyLink
Contact: Terry Huff, 206-345-5344 (office) or 206-794-8604 (cell)

Project: Aerial Cable Project
Location: Meridian Park Neighborhood
About: Qwest/CenturyLink will place 8400 lineal feet of aerial fiber optic cable and install five (5) new utility poles. The work will take place west of I-5 on N 167 St, north on Meridian Ave N, east on N 178 St, north on 1st Ave NE, east on NE 180 St, north on 3 Ave NE, east on NE 185 St to 5 Ave NE.
Schedule: Anticipated schedule is the week of June 13th to late Fall 2011..

Impacts: Expect traffic delays. Hours of operation are 9:00am to 3:00pm on arterial streets and 7:00am to 5:00pm on local streets.